Rue Général Capiaumont 62
Etterbeek · PU/558900 · Permis d'urbanisme privé
Rue Général Capiaumont 62, Etterbeek: split into dwellings. Case octroyé, lodged on 19 February 2015. The decision was notified on 28 September 2015, 221 days after lodging. The project creates 37 m² of housing. It comprises 1 dwellings.
régulariser la création d'un studio dans les combles et les aménagements intérieurs d'un immeuble| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 February 2015 | date the file was received |
| Decision notified | 28 September 2015 | 221 days |
| Competent authority | Etterbeek |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 16 m | Extension or raising | agrandir et rénover une maison unifamiliale afin de la diviser en 3 logements | 2023 |
| 16 m | Extension or raising | modifier le permis d'urbanisme 11861 en ce qui concerne les aménagements intérieurs et les modifications extérieures MOD | 2025 |
| 24 m | Façade and windows | modifier la couleur des vitrages (de jaune vers blanc) en façade avant | 2022 |
| 38 m | Tree felling | abattre un arbre en zone de cours et jardins | 2023 |
| 48 m | Change of use | modifier l'affectation du rez-de-chaussée de commerce en logement, agrandir et étendre l'appartement du 3e étage vers le | 2025 |
Other nearby cases : 05/PU/1994531, 05/PU/1954108, 05/PU/1868958, 05/PU/2031594, 05/PU/1833298, 05/PFD/1903529, 05/PU/1827746, 05/PU/2014272, 05/PU/2022497, 05/PU/1893683, 05/PU/1994756, 05/PU/1994757, 05/PU/2044840, 05/PU/1989050, 05/PU/1837183, 05/PU/1999110, 05/PU/1928915, 05/PU/1844250, 05/PU/1926140, 05/PU/1894252, 05/PU/2022636, 05/PU/1941137, 05/ENS/2030016, 05/PU/1926271, 05/PFU/1988115
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)