Rue du Craetveld /
Bruxelles · PU/559419 · Permis d'urbanisme privé
Rue du Craetveld /, Bruxelles: tree felling. Case octroyé, lodged on 26 February 2015. The decision was notified on 11 February 2016, 350 days after lodging.
abattre 4 arbres| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 26 February 2015 | date the file was received |
| Decision notified | 11 February 2016 | 350 days |
| Works started | 30 March 2016 | |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 28 m | Other | J'envisage de réaliser une rampe d'accées pour chaise roulante,les spécifications techniques suivantes : plate forme de | 2025 |
| 28 m | Extension or raising | placer une rampe d'accès pour chaise roulante devant la porte d'entrée et construire une véranda | 2025 |
| 140 m | Tree felling | abattre un arbre (machoire) | 2023 |
| 149 m | New construction | construire une maison unifamiliale 3 façades avec 4 chambres et un garage dans le lotissement AN1596 - lot 38 | 2022 |
| 150 m | New construction | Construire un nouveau bâtiment scolaire devant accueillir un DOA (degré d'observation autonome) d'environ 500 élèves. | 2022 |
Other nearby cases : 04/PU/1939185, 04/PU/1918321, 04/PU/1828949, 04/PU/1858766, 04/PU/1942554, 04/PU/1907144, 04/PU/1849354, 04/PU/1934980, 04/PU/1826940, 04/PU/1898583, 04/PU/2040184, 04/PU/1895303, 04/PU/1961992, 04/PU/1837465, 04/PU/1863293, 04/PU/1801436, 04/PU/1926536, 04/PU/1820340, 04/PU/1979765, 04/PU/1894325, 04/GOU_PU/1841184, 04/PU/1799955, 04/PFD/1991593
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)