Granted
Chemin des Pins 10
Uccle · PU/561660 · Permis d'urbanisme privé
Chemin des Pins 10, Uccle: —. Case octroyé, lodged on 3 April 2015. The decision was notified on 2 February 2016, 305 days after lodging. The project creates 23 m² of housing.
23m²
Housing floor area created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 3 April 2015 | date the file was received |
| Decision notified | 2 February 2016 | 305 days |
| Competent authority | Uccle |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)