Granted
Rue du Kriekenput 4
Uccle · PU/561678 · Permis d'urbanisme privé
Rue du Kriekenput 4, Uccle: extension or raising. Case octroyé, lodged on 3 April 2015. The decision was notified on 13 November 2015, 224 days after lodging. The project creates 105 m² of housing.
l’isolation par l’extérieur d’une maison unifamiliale et la mise en conformité de l’extension réalisée côté jardin105m²
Housing floor area created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 3 April 2015 | date the file was received |
| Public inquiry | 1 June 2015 – 16 June 2015 | |
| Consultation committee | 1 July 2015 | |
| Decision notified | 13 November 2015 | 224 days |
| Competent authority | Uccle |
Timeline
- Application lodged
- Declared incomplete
- Public inquiry opened
- Declared complete
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- event_works_ended
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 23 m | Tree felling | Abattage de deux arbres | 2023 |
| 23 m | Tree felling | Abattage de deux arbres | 2023 |
| 23 m | Heavy renovation | construire une piscine écologique et transformer une partie du garage existant en poolhouse | 2025 |
| 60 m | Tree felling | abattre un bouleau | 2025 |
| 102 m | Public space | Rénover le pont de l'avenue des Tilleuls afin d’assurer la sécurité du personnel et la pérennité l’ouvrage : - renouvele | 2026 |
Other nearby cases : 16/PU/1983382, 16/PU/2027563, 16/PU/1835672, 16/SFD/1851771, 16/PU/1849339, 16/PU/1828191, 16/PU/1859970, 16/PU/1846330, 16/PFD/1907691, 16/PU/1988854, 16/PU/1922490, 16/SFD/1935703, 16/PU/1936747, 16/AA/1823406, 16/PU/1799695, 16/PU/1822288, 16/PU/1992426
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)