Granted
Avenue Houba de Strooper 788
Bruxelles · PU/563095 · Permis d'urbanisme privé
Avenue Houba de Strooper 788, Bruxelles: extension or raising. Case octroyé, lodged on 4 May 2015. The decision was notified on 9 October 2017, 889 days after lodging. The project creates 113 m² of housing. It comprises 3 dwellings.
transformer la maison unifamiliale afin d'y aménager 3 logements et construire une annexe au rez-de-chaussée113m²
Housing floor area created
3
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 4 May 2015 | date the file was received |
| Public inquiry | 24 February 2017 – 11 March 2017 | |
| Consultation committee | 28 March 2017 | |
| Decision notified | 9 October 2017 | 889 days |
| Works started | 2 April 2018 | |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Change of use | d'une part, construire une véranda (mise en conformité) ; et d'autre part, changer la destination du garage de logement | 2022 |
| 128 m | Tree felling | abattre 10 frênes | 2025 |
| 129 m | Extension or raising | fermer une terrasse au niveau du sous-sol (niveau jardin) | 2022 |
| 141 m | Demolition and reconstruction | Avenue Houba de Strooper, d'une part, diviser une maison unifamiliale en 3 studios et un rez-de-chaussée commercial, ave | 2021 |
| 145 m | Tree felling | Abattre un arbre à haute tige (sapin) | 2025 |
Other nearby cases : 04/PU/1946799, 04/PU/1941001, 04/PU/1821727, 04/PU/1835197, 04/PU/1831946
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)