Granted

Place Rouppe 1

Bruxelles · PU/567441 · Permis d'urbanisme privé

Place Rouppe 1, Bruxelles: change of use. Case octroyé, lodged on 8 July 2015. The decision was notified on 19 November 2015, 134 days after lodging.

wijzigen van het gebruik van een bestaande handelszaak naar een snack (expresso & slow coffee bar)
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on8 July 2015date the file was received
Decision notified19 November 2015134 days
Works started14 December 2015
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted
  4. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.