Skip to content
Altaica Urban
Withdrawn

Clos du Bergoje 39–41

Auderghem · PU/574275 · Permis d'urbanisme privé

Clos du Bergoje 39–41, Auderghem: new construction. Case annulé, lodged on 11 December 1987.

construction immeuble à appart (phase 3)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusAnnulé
Lodged on11 December 1987date the file was received
Floor areasnot reported by the source
Competent authorityAuderghem

Timeline

  1. Application lodged

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
60 mHeavy renovationouvrir une baie vitrée, réorganiser l'intérieur de la maison unifamiliale2024
62 mFaçade and windowsremplacer les 2 portes de garage basculantes par des portes sectionnelles2023
62 mFaçade and windowsmettre en conformité la modification de 2 baies en façade avant2025
62 mFaçade and windowsremplacer les 2 portes de garage basculantes par des portes sectionnelles2024
63 mFaçade and windowsremplacer la porte de garage en façade avant d'une maison unifamiliale2025

Other nearby cases : 02/SFD/2035767, 02/PU/1977360, 02/PU/1979719, 02/PU/1968764, 02/PU/1908497, 02/PFD/2017593, 02/PU/2037847, 02/PU/1846532, 02/PFD/2042023, 02/PU/1938449, 02/PU/1841455, 02/PFU/1949907, 02/PU/2020993, 02/PU/2044680, 02/PU/1941851, 02/PU/1821692, 02/PU/2043442, 02/PU/1918805, 02/PU/1956814, 02/PU/1801301, 02/GOU_PU/1835667, 02/PFD/1962552, 02/GOU_PU/1987259, 02/PU/1838873, 02/PU/1927019

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)