Granted
Clos des Pleurotes 1
Anderlecht · PU/584352 · Permis d'urbanisme privé
Clos des Pleurotes 1, Anderlecht: new construction. Case octroyé, lodged on 26 October 2015. The decision was notified on 18 April 2016, 175 days after lodging. The project creates 311 m² of housing.
bouwen van een ééngezinswoning in half-open bebouwing (lot 29)311m²
Housing floor area created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 26 October 2015 | date the file was received |
| Decision notified | 18 April 2016 | 175 days |
| Works started | 1 June 2016 | |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)