Woluwe-Saint-Pierre · PU/584477 · Permis d'urbanisme privé
Stuyvenberg 9, Woluwe-Saint-Pierre: extension or raising. Case octroyé, lodged on 17 November 2015. The decision was notified on 10 February 2016, 85 days after lodging.
Modification de volume et transformation de l'habitation unifamiliale mitoyenne| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 17 November 2015 | date the file was received |
| Public inquiry | 23 November 2015 – 8 December 2015 | |
| Consultation committee | 17 December 2015 | |
| Decision notified | 10 February 2016 | 85 days |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 24 m | Heavy renovation | transformation d'une maison unifamiliale | 2024 |
| 31 m | Roof | aménager des combles et créer une lucarne pour une maison unifamiliale | 2022 |
| 31 m | Façade and windows | régulariser les menuiseries extérieures et modifier les balcons et les garde-corps de l'immeuble | 2025 |
| 73 m | Tree felling | abattre un arbre en zone de cours et jardins | 2025 |
| 80 m | Extension or raising | Transformer et étendre l'immeuble bi-familial | 2022 |
Other nearby cases : 19/PU/1944859, 19/PU/1976289, 19/PU/1996454, 19/PU/1944219, 19/AA/1963035, 19/PU/1941961, 19/PU/1953764, 19/PU/2002385, 19/PU/2011479, 19/PU/1923903, 19/PU/2039135, 19/LPFD/1905901, 19/PU/1897058, 19/PU/1983110, 19/PU/2016897, 19/PU/1942574, 19/PU/1924068, 19/GOU_PU/1953179, 19/PU/1846377, 19/PU/1936894, 19/PU/1939196, 19/PU/2032150, 19/PU/2009294, 19/PU/2009144, 19/PU/1893762
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)