Rue Bruyn 82, Bruxelles: new construction. Case octroyé, lodged on 19 November 2015. The decision was notified on 24 February 2016, 97 days after lodging. The project creates 261 m² of housing.
construire une maison unifamiliale rez+2+T261m²
Housing floor area created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 November 2015 | date the file was received |
| Decision notified | 24 February 2016 | 97 days |
| Works started | 15 August 2016 | |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)