Skip to content
Altaica Urban
Granted

Rue Pierre Mattheussens 39

Evere · PU/592000 · Permis d'urbanisme privé

Rue Pierre Mattheussens 39, Evere: new construction. Case octroyé, lodged on —.

cosntruire une remise
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on
Decision notified30 August 1933
Floor areasnot reported by the source
Competent authorityEvere

Timeline

  1. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
33 mExtension or raisingmettre en conformité les travaux réalisés (extension, modification de l'aspect de la façade avant)2025
35 mNew constructionconstruire un immeuble de logements (6 logements et un bureau pour profession libérale)2022
50 mHeavy renovationtransformer et rénover une maison unifamiliale.2023
56 mRegularisationmettre en conformité les modifications réalisées dans la zone de parking.2024
58 mChange of usemodifier la destination du bâtiment en intérieur d'îlot (d'atelier d'emballage à entrepôt et parking ) et mettre en conf2023

Other nearby cases : 06/PU/1965426, 06/PU/1858578, 06/PU/1905497, 06/PU/2030088, 06/PU/1971698, 06/PU/2019936, 06/PU/2042875, 06/PU/1921662, 06/SFD/1979076, 06/PU/1957350, 06/PU/1918658, 06/PU/1989396, 06/PU/2032618, 06/PU/1893916, 06/PU/1981482, 06/SFD/2009326, 06/SFD/1965402, 06/PU/1933337, 06/PU/1925270, 06/PU/2022372, 06/SFD/1824681, 06/PFD/1829452, 06/PU/1910759, 06/PU/1823633, 06/SFD/1910079

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)