Granted

Rue Belliard 80

Bruxelles · PU/592915 · Permis d'urbanisme privé

Rue Belliard 80, Bruxelles: regularisation. Case octroyé, lodged on 18 February 2016. The decision was notified on 20 May 2016, 92 days after lodging.

modifier les permis d'urbanisme B66/2011, B1132/2014 et B570/2015, apporter des modifications mineures à un immeuble de bureaux (plans as built)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on18 February 2016date the file was received
Decision notified20 May 201692 days
Works started3 June 2016
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Decision notified · Granted
  3. Declared complete
  4. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
24 mPublic spaceMettre en place des éléments de sécurisation du pourtour du bâtiment WIM : - murets en béton armé au pied des colonnes a2024
54 mHeavy renovationModifier la configuration d'un local chaufferie au niveau -022021
60 mSplit into dwellingsmodifier le permis B1307/2018 : modifier les installations techniques, maintenir le mur de soutènement existant, réaména2025
62 m04/PU/19078782023
62 mHeavy renovationmodifier le permis B1307/2018 : réaménager les sous-sols et modifier les circulations verticales2022

Other nearby cases : 04/SFD/1826529, 04/PU/1942294, 04/SFD/1925138, 04/PFD/1994547, 04/PFD/1829135, 04/PFD/1950847, 04/PU/1851851, 04/PU/1939568, 04/PU/1932336, 04/PU/2012327, 04/PFD/1859327, 04/PU/1833726, 04/PFD/1993947, 04/PFD/1837811, 04/PU/1908232, 04/PU/1968113, 04/SFD/1863005, 04/PU/2044132, 04/PU/2003487, 04/PFU/2003356, 04/PFD/1891951, 04/PFD/2006647, 04/PFD/1826203, 04/PFU/1929200, 04/PFU/1930817

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)