Granted
Rue Saint-Josse 2–4
Saint-Josse-ten-Noode · PU/597539 · Permis d'urbanisme privé
Rue Saint-Josse 2–4, Saint-Josse-ten-Noode: change of use. Case octroyé, lodged on 6 April 2016. The decision was notified on 19 July 2016, 104 days after lodging. The project creates 49 m² of housing.
modifier l'affectation d'un commerce en un studio avec modification des baies au rez-de-chaussée49m²
Housing floor area created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 6 April 2016 | date the file was received |
| Decision notified | 19 July 2016 | 104 days |
| Works started | 9 September 2016 | |
| Competent authority | Saint-Josse-ten-Noode |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)