Granted
Avenue des Lauriers 37
Woluwe-Saint-Pierre · PU/602234 · Permis d'urbanisme privé
Avenue des Lauriers 37, Woluwe-Saint-Pierre: new construction. Case octroyé, lodged on 1 June 2016. The decision was notified on 25 July 2016, 54 days after lodging. The project creates 466 m² of housing.
Construction d'une rampe extérieure d'accès à un garage en sous-sol en intérieur d'ilot466m²
Housing floor area created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 June 2016 | date the file was received |
| Public inquiry | 6 June 2016 – 21 June 2016 | |
| Consultation committee | 23 June 2016 | |
| Decision notified | 25 July 2016 | 54 days |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 40 m | New construction | démonter le terrain de tennis et construire un abri de jardin pour la piscine | 2025 |
| 52 m | Other | construction d'une piscine et d'un poolhouse en zone de cours et jardins d'une maison unifamiliale 4 façades | 2026 |
| 56 m | Other | construire une piscine et un poolhouse dans la zone de cours et jardin | 2025 |
| 59 m | New construction | construction de 2 maisons unifamiliales et d'une piscine avec poolhouse | 2024 |
| 178 m | Heavy renovation | transformer et régulariser l'habitation unifamiliale 4 façades | 2024 |
Other nearby cases : 19/PU/2025491, 19/PU/1966814, 19/AA/1915123, 19/PU/1935276, 19/PU/1862160, 19/PU/1907203, 19/SFD/1825807
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)