Place Colignon 046
Schaerbeek · PU/604848 · Permis d'urbanisme privé
Place Colignon 046, Schaerbeek: extension or raising. Case octroyé, lodged on 7 July 2016. The decision was notified on 14 June 2017, 342 days after lodging. The project creates 4 m² of housing. It creates 6 m² of office space.
Dans un immeuble mixte (bureau et logement) construire des annexes au rez-de-chaussée et 2ème étage| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 July 2016 | date the file was received |
| Decision notified | 14 June 2017 | 342 days |
| Competent authority | Schaerbeek |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 8 m | Energy works | [CADUC] dans une maison unifamiliale, placer 8 panneaux photovoltaïques sur le versant avant | 2022 |
| 12 m | Extension or raising | dans une maison unifamiliale, modifier la volumétrie en façade arrière, réaliser des travaux structurels, mettre en conf | 2025 |
| 35 m | Other | Test construire sans archi | 2023 |
| 39 m | Façade and windows | REALISE - dans un immeuble comprenant un commerce et un logement, placer un conduit d'évacuation de hotte en façade arri | 2025 |
| 39 m | Change of use | REALISE - dans un immeuble comprenant un commerce au rez-de-chaussée et un logement aux étages, changer l'affectation du | 2023 |
Other nearby cases : 15/PU/2006204, 15/PU/1957382, 15/PFU/1811012, 15/PFU/2041255, 15/PU/1829595, 15/PU/1846630, 15/PU/1961797, 15/PU/1831069, 15/PFD/1832324, 15/PFD/1913014, 15/PFD/1941933, 15/PU/1900762, 15/GOU_PU/1926705, 15/PU/2010048, 15/PU/1839075, 15/SFD/1821954, 15/PU/2036652, 15/PU/1970314, 15/PFU/1912799, 15/PFU/1908060, 15/SFD/1825062, 15/PU/1988435, 15/PU/2014894, 15/PU/1845226, 15/PU/1902753
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)