Rue Richard Braibant 20
Ganshoren · PU/609115 · Permis d'urbanisme privé
Rue Richard Braibant 20, Ganshoren: new construction. Case octroyé, lodged on 23 August 2016. The decision was notified on 18 April 2017, 238 days after lodging. The project creates 167 m² of housing.
construire une maison unifamiliale| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 23 August 2016 | date the file was received |
| Public inquiry | 30 January 2017 – 14 February 2017 | |
| Consultation committee | 28 February 2017 | |
| Decision notified | 18 April 2017 | 238 days |
| Works started | 22 May 2017 | |
| Competent authority | Ganshoren |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
- event_works_ended
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 15 m | Heavy renovation | transformer une maison unifamiliale | 2024 |
| 26 m | Tree felling | Abattage d'un arbre | 2025 |
| 26 m | Tree felling | Abattage d'un arbre | 2024 |
| 39 m | Heavy renovation | rénover une maison unifamiliale | 2024 |
| 39 m | Energy works | placer une pompe à chaleur | 2026 |
Other nearby cases : 08/PU/2025036, 08/PU/2004336, 08/PU/1958361, 08/PU/1998295, 08/PU/2002045, 08/PU/2005940, 08/PU/2019628, 08/PU/2004281, 08/PU/1852757, 08/PU/1834190, 08/PU/1911978, 08/PU/2028689, 08/PU/1824650, 08/PU/2044890, 08/PU/1975294, 08/PU/1949648, 08/PU/2015828, 08/PU/1858653, 08/PU/1989041, 08/PU/1903450, 08/PU/1925938, 08/PU/1965646, 08/PU/1832990, 08/GOU_PU/1844221, 08/PU/1846245