Skip to content
AltUrb
Granted

Rue de l'Electricité 38

Anderlecht · PU/610201 · Permis d'urbanisme privé

Rue de l'Electricité 38, Anderlecht: regularisation. Case octroyé, lodged on 2 September 2016. The decision was notified on 4 April 2018, 579 days after lodging. The project creates 74 m² of housing.

mettre en conformité une maison unfamiliale
The application's own description, in its source language (FR). Source: Nova.
74
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on2 September 2016date the file was received
Decision notified4 April 2018579 days
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.