Rue des Commerçants 48–52, Bruxelles: student housing. Case octroyé, lodged on 14 September 2016. The decision was notified on 30 July 2018, 684 days after lodging. The project creates 1 841 m² of housing. It comprises 46 dwellings.
slopen van het bestaande gebouw (met behoud van de straatgevel en de kelder) en bouwen van 46 studentenkoten1 841m²
Housing floor area created
46
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 September 2016 | date the file was received |
| Public inquiry | 16 March 2018 – 31 March 2018 | |
| Consultation committee | 24 April 2018 | |
| Decision notified | 30 July 2018 | 684 days |
| Works started | 18 May 2019 | |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)