Skip to content
AltUrb
Granted

Clos du Bolet 22

Anderlecht · PU/616659 · Permis d'urbanisme privé

Clos du Bolet 22, Anderlecht: new construction. Case octroyé, lodged on 9 November 2016. The decision was notified on 30 June 2017, 233 days after lodging. The project creates 363 m² of housing.

construire une maison unifamiliale
The application's own description, in its source language (FR). Source: Nova.
363
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on9 November 2016date the file was received
Decision notified30 June 2017233 days
Works started28 August 2017
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted
  4. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
17 mNew constructionconstruire une habitation unifamiliale2023
24 mExtension or raisingétendre une maison unifamiliale par la construction d'un garage couvert au rez-de-chaussée et d'une chambre à l'étage2022
38 mSigns and advertisingmaintenir un dispositif publicitaire de 15m² sur pignon2025
42 mNew constructionconstruire une habitation unifamiliale2021
42 mNew constructionconstruire une habitation unifamiliale2023

Other nearby cases : 01/PU/1834347, 01/PU/1841320, 01/PU/1972728, 01/PU/1860408, 01/PU/1871031, 01/PU/2011650, 01/PU/1975642, 01/PU/1869442, 01/SFD/2004240, 01/PU/2013694, 01/PU/1907717, 01/PU/1994771, 01/PU/1991887, 01/PU/2026052, 01/PU/2031714, 01/PFD/1991786, 01/PFD/1909720

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)