Skip to content
Altaica Urban
Granted

Avenue de Mai 65

Woluwe-Saint-Lambert · PU/618415 · Permis d'urbanisme privé

Avenue de Mai 65, Woluwe-Saint-Lambert: extension or raising. Case octroyé, lodged on 23 November 2016. The decision was notified on 19 June 2017, 208 days after lodging. The project creates 92 m² of housing.

rénover, agrandir et rehausser la maison unifamiliale
The application's own description, in its source language (FR). Source: Nova.
92
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on23 November 2016date the file was received
Public inquiry13 April 2017 – 28 April 2017
Consultation committee12 May 2017
Decision notified19 June 2017208 days
Works started11 September 2017
Competent authorityWoluwe-Saint-Lambert

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted
  7. Works started
  8. event_works_ended

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
42 mSplit into dwellingsrégulariser l'aménagement d'un logement au 3e étage de l'immeuble2025
47 mFaçade and windowsCLASSE SANS SUITE : régulariser les travaux effectués et placer des screens en façade avant de la maison unifamiliale2024
55 mExtension or raisingrégulariser les travaux effectués (la construction d'une annexe en façade arrière, le remplacement des menuiseries extér2025
57 mRoofconstruire une lucarne sur le versant de toiture arrière de la maison unifamiliale2022
62 mExtension or raisingrégulariser le remplacement des menuiseries extérieures en façade avant, abattre deux arbres sur la parcelle, étendre le2025

Other nearby cases : 18/PU/2026022, 18/PU/1972129, 18/PU/1896164, 18/PU/1950312, 18/PU/1909367, 18/PU/1961782, 18/PU/1837635, 18/PU/1912548, 18/PU/1909576, 18/PU/2000570, 18/PU/1990502, 18/PU/1908863, 18/PU/2024524, 18/PU/1857677, 18/PU/1999708, 18/PU/1938141, 18/PU/2013933, 18/PU/1836196, 18/PU/1922857, 18/PU/1833771, 18/PU/1837243, 18/PU/1930441, 18/PU/1989895, 18/PU/1951889, 18/PU/1996836

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)