Rue Stuyvenbergh 3
Bruxelles · PU/619032 · Permis d'urbanisme privé
Rue Stuyvenbergh 3, Bruxelles: split into dwellings. Case refusé, lodged on 28 November 2016. The decision was notified on 5 March 2018, 462 days after lodging. It comprises 4 dwellings.
verdelen van een gebouw in 4 wooneenheden (reeds uitgevoerde werken)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Refusé | |
| Lodged on | 28 November 2016 | date the file was received |
| Decision notified | 5 March 2018 | 462 days |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Refused
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 11 m | Retail or horeca fit-out | d’une part, apporter des transformations structurelles intérieures, reboucher les baies de façade, placer une gaine d’ex | 2024 |
| 11 m | Signs and advertising | placer une enseigne parallèle lumineuse "BELCHICKEN" sur le toit de la terrasse fermée | 2023 |
| 43 m | Split into dwellings | diviser une maison unifamiliale en deux unités de logement (un studio et un duplex) | 2025 |
| 70 m | Signs and advertising | placer 1 mobilier urbain d’information avec support de publicité (BXL0534MU) | 2021 |
| 72 m | Tree felling | abattre un arbre à haute tige (érable) | 2023 |
Other nearby cases : 04/PU/1834983, 04/PU/2007797, 04/PU/1902330, 04/PU/1911666, 04/PU/1935399, 04/PU/1861097, 04/PU/1940441, 04/PU/1800538, 04/PU/1963200, 04/PU/1830118, 04/PU/1822079, 04/PU/2015172, 04/PU/1971092, 04/PU/1929620, 04/PU/1896023, 04/PU/2002251, 04/SFD/1904579, 04/PU/1930431, 04/PU/1897339, 04/PU/1871569, 04/PU/1901344, 04/PU/2025921, 04/PU/1938756, 04/PFD/1951828, 04/PU/1864948
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)