Granted
Rue de Percke 119A
Uccle · PU/627681 · Permis d'urbanisme privé
Rue de Percke 119A, Uccle: other. Case octroyé, lodged on 15 February 2017. The decision was notified on 22 June 2017, 127 days after lodging.
construction d'une piscine| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 February 2017 | date the file was received |
| Decision notified | 22 June 2017 | 127 days |
| Competent authority | Uccle |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 61 m | Tree felling | Abattre un arbre | 2026 |
| 71 m | Heavy renovation | rénover une maison unifamiliale, via des modifications intérieures structurelles, le remplacement des menuiseries, les a | 2024 |
| 71 m | Heavy renovation | rénover une maison unifamiliale - dossier remplacé par 16-48095-2025 | 2024 |
| 71 m | Extension or raising | transformer une maison unifamiliale et ses abords: remplacement des garde-corps existants afin de répondre aux normes de | 2025 |
| 71 m | Heavy renovation | rénover une maison unifamiliale, via des modifications intérieures structurelles, le remplacement des menuiseries, les a | 2024 |
Other nearby cases : 16/PFU/1980271, 16/SFD/1824951, 16/PU/1922517, 16/PU/1823530, 16/PU/1976227, 16/AA/1924878, 16/AA/1871488, 16/PFU/1994779, 16/PU/1994896, 16/PFD/1931700, 16/SFD/1841309, 16/AA/1951976, 16/GOU_PU/1961179, 16/AA/1902855, 16/PU/2036432, 16/AA/1843630, 16/PU/1942804