Granted

Drève des Madones 4

Auderghem · PU/631299 · Permis d'urbanisme privé

Drève des Madones 4, Auderghem: new construction. Case octroyé, lodged on 15 March 2017. The decision was notified on 29 August 2017, 167 days after lodging. The project creates 592 m² of housing.

construire une maison unifamiliale 4 façades
The application's own description, in its source language (FR). Source: Nova.
592
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on15 March 2017date the file was received
Public inquiry4 May 2017 – 19 May 2017
Consultation committee1 June 2017
Decision notified29 August 2017167 days
Works started25 January 2018
Competent authorityAuderghem

Timeline

  1. Application lodged
  2. Public inquiry opened
  3. Public inquiry closed
  4. Consultation committee
  5. Decision notified · Granted
  6. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
54 mDemolition and reconstructiondémolir et reconstruire une maison unifamiliale2023
54 mDemolition and reconstructiondémolir et reconstruire une habitation2023
54 mTree fellingabattre 5 arbres2021
54 mDemolition and reconstructiondémolir et reconstruire une maison unifamiliale 4 façades2024
70 mHeavy renovationrénover une maison unifamiliale2021

Other nearby cases : 02/AA/1973412, 02/AA/2004906, 02/PU/1863102, 02/PU/1844861, 19/AA/2003283, 02/AA/2004041, 02/PU/1925250, 19/PU/1939812, 02/PU/1957233, 02/PU/1834819, 02/PU/1940271, 19/PU/1894152, 19/PU/1996059, 02/PU/1902670, 19/AA/1834092, 02/PU/1867647, 02/PU/1966169, 02/PU/1903794, 02/PU/1929628

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)