Rue du Géomètre 30, Molenbeek-Saint-Jean: new construction. Case refusé, lodged on 21 March 2017. The decision was notified on 20 December 2021, 1 735 days after lodging. The project creates 920 m² of housing. It comprises 9 dwellings.
la construction d'un immeuble de rapport (R+4) comprenant 9 logements et 9 emplacements de parking en sous-sol920m²
Housing floor area created
9
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Refusé | |
| Lodged on | 21 March 2017 | date the file was received |
| Public inquiry | 29 August 2017 – 13 September 2017 | |
| Consultation committee | 19 September 2017 | |
| Decision notified | 20 December 2021 | 1 735 days |
| Competent authority | Molenbeek-Saint-Jean |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Refused
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | New construction | la construction d'un immeuble de rapport mitoyen (R+4) comprenant 9 logements et 8 emplacements parking en sous-sol PM: | 2023 |
| 0 m | New construction | la construction d'un immeuble de rapport mitoyen (R+4) comprenant 9 logements et 8 emplacements parking en sous-sol PM: | 2024 |
| 127 m | New construction | construire un immeuble comprenant 41 logements d'une surface totale de 4 614,7m², 240,3m² de surface commercial, 349,4m | 2024 |
| 140 m | New construction | la construction d’une annexe de service avec monte-charge extérieur (gabarit R+2 - 60m2) et d’un parking à vélos et abri | 2026 |
| 140 m | Other | la mise en place et le raccordement d'une cabine haute tension de 800Kva | 2022 |
Other nearby cases : 12/PU/1914080, 12/PFD/2014049, 12/SFD/1925015, 12/PU/2016749, 12/PU/1992002, 12/PU/1850655, 12/PU/1930623, 12/PU/1819984, 12/PFD/1915227, 12/SFD/2015184, 12/PU/1939148, 12/PFD/2035546, 12/PFD/1999535, 12/PU/1906371, 12/PU/1811556
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)