Square Emile des Grées du Loû 5
Forest · PU/635839 · Permis d'urbanisme privé
Square Emile des Grées du Loû 5, Forest: demolition. Case octroyé, lodged on 24 April 2017. The decision was notified on 16 October 2017, 175 days after lodging. It removes 850 m² of office space.
Het afbreken van gebouwen850m²
Office floor area removed
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 24 April 2017 | date the file was received |
| Public inquiry | 4 September 2017 – 19 September 2017 | |
| Consultation committee | 3 October 2017 | |
| Decision notified | 16 October 2017 | 175 days |
| Competent authority | Forest |
Timeline
- Application lodged
- Declared incomplete
- Public inquiry opened
- Declared complete
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 74 m | Extension or raising | rehausser un escalier de secours | 2021 |
| 77 m | New construction | Construire un volume en supprimant des emplacements pour véhicules motorisés | 2022 |
| 160 m | Extension or raising | Travaux de préparation du terrain en vue d’étendre la zone logistique existante AP/4 et d’y construire ultérieurement un | 2022 |
| 184 m | Demolition | démolir des bâtiments existants | 2023 |
| 203 m | New construction | Construire et exploiter une grande éolienne et ses accessoires dans le cadre de la production d'énergie verte, installer | 2024 |
Other nearby cases : 07/PFD/1896583, 07/PFD/1915784, 07/PU/1974500, 07/PU/1940045