Granted
Allée de la Recherche 60
Anderlecht · PU/644273 · Permis d'urbanisme privé
Allée de la Recherche 60, Anderlecht: heavy renovation. Case octroyé, lodged on 11 July 2017. The decision was notified on 19 December 2017, 161 days after lodging. It removes 99 m² of office space.
créer un auditoire + réaménagement des plateaux99m²
Office floor area removed
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 11 July 2017 | date the file was received |
| Decision notified | 19 December 2017 | 161 days |
| Works started | 12 January 2018 | |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Other | installer une infrastructure (dalle/zone technique) pour accueillir des installations/ machines techniques (groupes de f | 2026 |
| 148 m | Extension or raising | transformer une maison unifamiliale : agrandissement à l’arrière, aménagements garage et abris de jardin en fond de parc | 2026 |
| 213 m | Energy works | aménager 8 emplacements destinés à la recharge des voitures électrique, installer 4 bornes de recharge pour véhicule éle | 2024 |
| 213 m | Façade and windows | rénover les façades et enseignes du restaurant "Quick Erasme" par l'ajout d'un auvent pour un guichet drive-in et la mod | 2025 |
| 221 m | New construction | Afbraak van een bestaande garage. Bouwen van 20 appartementen en een handelspand. Opwaardering van een intensief gemaaid | 2026 |
Other nearby cases : 01/PFD/1931286, 01/PU/2022132, 01/PU/2002402, 01/PU/1988691
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)