Granted

Rue Edouard Stuckens 148A

Evere · PU/648535 · Permis d'urbanisme privé

Rue Edouard Stuckens 148A, Evere: extension or raising. Case octroyé, lodged on 18 August 2017. The decision was notified on 21 December 2017, 125 days after lodging. The project creates 8 m² of housing.

mettre en conformité l'extension du 1er étage.
The application's own description, in its source language (FR). Source: Nova.
8
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on18 August 2017date the file was received
Public inquiry25 September 2017 – 10 October 2017
Consultation committee19 October 2017
Decision notified21 December 2017125 days
Competent authorityEvere

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Declared complete
  7. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mChange of usemodifier partiellement la destination du rez-de-chaussée (atelier) en logement (studio).2025
0 mChange of usemodifier partiellement la destination du rez-de-chaussée (atelier) en logement (studio).2023
24 mRegularisationmettre en conformité les travaux réalisés.2023
30 mExtension or raisingmettre en conformité les transformations apportées à une maison unifamiliale, l'étendre en intérieur d'îlot et rehausser2022
30 mSplit into dwellingsdiviser une maison unifamiliale en 4 unités de logements.2023

Other nearby cases : 06/PU/2013168, 06/PU/1997588, 06/PU/1896785, 06/PU/2020061, 06/PU/2026957, 06/PU/1850356, 06/PU/1835532, 06/PU/1848850, 06/SFD/1910092, 06/PU/1934383, 06/PU/1900764, 06/PU/1916975, 06/PU/1843638, 06/PU/1912367, 06/SFD/1904597, 06/PU/1862036, 06/PU/1989893, 06/SFD/1946833, 06/PU/1912693, 06/PU/1916971, 06/PU/1842845, 06/PU/2035994, 06/PU/1992514, 06/PU/2002481, 06/PU/2011478

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)