Avenue Norbert Gille 23
Anderlecht · PU/651298 · Permis d'urbanisme privé
Avenue Norbert Gille 23, Anderlecht: roof. Case octroyé, lodged on 14 September 2017. The decision was notified on 18 May 2018, 246 days after lodging.
mettre en conformité les travaux réalisés, isoler la toiture & remplacer une lucarne arrière par 2 velux| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 September 2017 | date the file was received |
| Decision notified | 18 May 2018 | 246 days |
| Works started | 24 September 2018 | |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 42 m | Façade and windows | remplacer les châssis d'une maison unifamiliale | 2024 |
| 70 m | Split into dwellings | mettre en conformité un immeuble en 2 triplex et améliorer sa performance énergétique | 2024 |
| 76 m | Extension or raising | étendre un immeuble de rapport existant via la construction d'un duplex | 2022 |
| 76 m | Extension or raising | étendre un immeuble de rapport existant via la construction d'un duplex | 2024 |
| 77 m | Split into dwellings | construire un logement supplémentaire + réaménager 2 appartements | 2025 |
Other nearby cases : 01/PU/1964998, 01/PU/1910219, 01/PFD/1930860, 01/PU/1937844, 01/SFD/1990904, 01/GOU_PU/2015969, 01/PU/2033352, 01/PU/1992534, 01/PFD/1966640, 01/PU/1911479, 01/PU/2027605, 01/PU/1934929, 01/PU/2009524, 01/PU/1966386, 01/PU/1927023, 01/PU/1998362, 01/PU/1799753, 01/PU/1964360, 01/PU/1824440, 01/PU/1911068, 01/PU/1897382, 01/PU/1901258, 01/PU/1825213, 01/PU/2019238, 01/SFD/1998960
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)