Granted
Rue des Papillons 290 A
Anderlecht · PU/653092 · Permis d'urbanisme privé
Rue des Papillons 290 A, Anderlecht: heavy renovation. Case octroyé, lodged on 3 October 2017. The decision was notified on 31 August 2018, 332 days after lodging. The project creates 34 m² of housing.
verbouwen van een ééngezinswoning34m²
Housing floor area created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 3 October 2017 | date the file was received |
| Public inquiry | 24 March 2018 – 8 April 2018 | |
| Consultation committee | 19 April 2018 | |
| Decision notified | 31 August 2018 | 332 days |
| Works started | 28 October 2019 | |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 93 m | Façade and windows | mettre en conformité la modification des fenêtres en façades avant + peindre la façade avant | 2022 |
| 180 m | Regularisation | mettre en conformité des constructions indispensables à l'exploitation et au logement des exploitants | 2022 |
| 180 m | Regularisation | mettre en conformité des constructions indispensables à l'exploitation et au logement des exploitants | 2023 |
| 204 m | New construction | mettre en conformité des infrastructures pour la pratique du maraîchage professionnel : serres-tunnel, container de stoc | 2025 |
| 204 m | New construction | mettre en conformité des infrastructures pour la pratique du maraîchage professionnel : serres-tunnel, container de stoc | 2025 |
Other nearby cases : 01/PU/1916713
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)