Skip to content
AltUrb
Granted

Avenue Broustin 80

Ganshoren · PU/659437 · Permis d'urbanisme privé

Avenue Broustin 80, Ganshoren: heavy renovation. Case octroyé, lodged on 12 December 2017. The decision was notified on 29 January 2018, 48 days after lodging. The project creates 12 m² of housing.

transformer l'appartement de droite au 3ième étage et régulariser la fermeture de la terrasse arrière
The application's own description, in its source language (FR). Source: Nova.
12
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on12 December 2017date the file was received
Decision notified29 January 201848 days
Competent authorityGanshoren

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
27 mExtension or raisingconstruire une annexe avec terrasse en toiture2021
29 mFaçade and windowsmettre en conformité le parking en intérieur d'îlot, l'entrée et la façade avant2022
39 mHeavy renovationTransformer une maison unifamiliale (régularisation d'un infraction)2021
46 mRegularisationMettre en conformité un appartement duplex + grenier2023
46 mFaçade and windowsmettre en conformité la façade avant2023

Other nearby cases : 08/PU/1954156, 08/PU/1945103, 08/SFD/1959303, 08/PU/1923928, 08/PU/2006525, 08/PU/1994692, 08/PU/1907845, 08/PFD/1946204, 08/PU/1859626, 08/PU/2015210, 08/PU/1945939, 08/PFU/1944766, 08/PU/1998233, 08/PU/1842676, 08/PU/1864877, 08/PU/2022490, 08/PU/1935750, 08/PU/1922330, 08/PU/1801628, 08/GOU_PU/2001928, 08/PU/1982347, 08/PU/1842161, 08/PU/2011859, 08/PU/1905551, 08/PU/1967741

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)