Granted

Boulevard Saint-Michel 2

Woluwe-Saint-Pierre · PU/661668 · Permis d'urbanisme privé

Boulevard Saint-Michel 2, Woluwe-Saint-Pierre: roof. Case octroyé, lodged on 17 April 2018. The decision was notified on 31 July 2018, 105 days after lodging.

bouwen van een dakkapel aan de voorkant van het dak van het woongebouw
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on17 April 2018date the file was received
Consultation committee21 June 2018
Decision notified31 July 2018105 days
Competent authorityWoluwe-Saint-Pierre

Timeline

  1. Application lodged
  2. Declared complete
  3. Consultation committee
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mRoofrégulariser une terrasse de toit2024
32 mChange of userégulariser l’affectation du bureau au rez-de-chaussée de l'immeuble2022
48 mTree fellingabattre un arbre en zone de cours et jardins2025
63 mExtension or raisingrégulariser la structure d'une tente solaire saisonnière dans la zone de recul du commerce2022
88 mHeavy renovationtransformer, aménager et régulariser l'entresol et le bel-étage de l'immeuble mitoyen2024

Other nearby cases : 19/PU/1947929, 19/PU/1966904, 05/PU/1957579, 05/PU/1955747, 19/PU/1996926, 19/PU/1869854, 05/PU/1956036, 05/PU/1900747, 19/PFD/1962500, 19/PFD/1904091, 05/PU/1962580, 05/PU/1850640, 05/PFD/2008237, 19/PU/1971666, 05/PU/1893423, 05/PU/1943942, 05/PU/1830468, 19/PU/1930377, 19/PU/1986945, 19/PU/1850053, 05/PU/1843209, 19/PU/1842359, 19/SFD/1827582, 19/PU/1901056, 19/PU/1939578

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)