Skip to content
AltUrb
Granted

Square Baron Robert Hankar 4

Auderghem · PU/662930 · Permis d'urbanisme privé

Square Baron Robert Hankar 4, Auderghem: change of use. Case octroyé, lodged on 22 December 1970. The decision was notified on 22 December 1970, 0 days after lodging.

transformer un garage en magasin
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on22 December 1970date the file was received
Decision notified22 December 19700 days
Floor areasnot reported by the source
Competent authorityAuderghem

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mChange of usechanger l'affectation d'un bureau en commerce au rez de chaussée d'un immeuble mixte2026
39 mTree fellingabattre 1 arbre2023
39 mTree fellingabattre 1 arbre2022
39 mRoofcréer une terrasse sur une partie de la toiture plate principale de l'immeuble2026
39 mFaçade and windowsremplacer la vitrine d'un commerce2025

Other nearby cases : 02/PU/1961625, 02/PU/2043750, 02/PU/1996902, 02/PU/1982037, 02/PU/2007262, 02/PU/1928208, 02/PU/1863317, 02/PU/1835846, 02/PU/1981839, 02/PU/2034745, 02/ENS/1928990, 02/PU/1957854, 02/PU/1957970, 02/PU/2041498, 02/PU/1914650, 02/PP/1911154, 02/PU/1916984, 02/PU/1839112, 02/PU/1938040, 02/PU/2007387, 02/PU/1968301, 02/PU/1834778, 02/PU/1899435, 02/SFD/1858741, 02/AA/1844404

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)