Avenue de la Houlette 39
Auderghem · PU/663496 · Permis d'urbanisme privé
Avenue de la Houlette 39, Auderghem: new construction. Case octroyé, lodged on 1 October 1971. The decision was notified on 1 October 1971, 0 days after lodging. It comprises 3 dwellings.
construire un immeuble à 3 logements| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 October 1971 | date the file was received |
| Decision notified | 1 October 1971 | 0 days |
| Floor areas | — | not reported by the source |
| Competent authority | Auderghem |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 36 m | Heavy renovation | rénover un immeuble de logements sociaux avec remplacement des châssis, isolation des façades aux étages et réaménagemen | 2022 |
| 36 m | Tree felling | abattre deux arbres et replanter trois arbres fruitiers à l'arrière d'un l'immeuble | 2024 |
| 46 m | Tree felling | abattre 3 arbres | 2022 |
| 52 m | Façade and windows | remplacer les garde-corps de la façade qui forme l'angle de la rue de la Houlette et de l'avenue des Gerfauts | 2023 |
| 68 m | Roof | rénover une toiture (isolation extérieur Sarking) | 2024 |
Other nearby cases : 02/PU/1916314, 17/PU/1826975, 17/PU/1856803, 02/PU/2015919, 02/PFD/1840884, 02/SFD/1830887, 02/PU/1850403, 17/PFD/1976268, 17/PU/1976862, 17/PFD/1977924, 02/PU/1992726, 02/PFD/1938515, 02/PU/1934684, 02/PU/1910212, 02/PU/1821869, 02/PU/1949552, 02/PU/1976433, 02/PU/2007733, 02/PU/1956910, 02/PU/2029562, 02/PFD/1847902, 02/PU/2019323, 17/PU/2008829, 17/PU/1845947, 17/PU/2008644
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)