Skip to content
AltUrb
Granted

Boulevard du Souverain 147

Auderghem · PU/671333 · Permis d'urbanisme privé

Boulevard du Souverain 147, Auderghem: new construction. Case octroyé, lodged on 2 October 1922. The decision was notified on 5 August 1964, 15 283 days after lodging.

construction cinéma (!!! plusieurs événements voir journal)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on2 October 1922date the file was received
Decision notified5 August 196415 283 days
Floor areasnot reported by the source
Competent authorityAuderghem

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
11 mHeavy renovationtransformer deux immeubles2026
25 mChange of usemettre en conformité le changement d'affectation d'une partie du rez-de-chaussée, isoler la façade arrière, les murs mit2024
37 mChange of usechanger la destination du commerce2026
48 mChange of useaménager une nouvelle porte d'accès en façade et modifier la destination de 3 studios au 5ème étage en une chambre d'iso2022
48 mChange of useaménager une nouvelle porte d'accès en façade et modifier la destination de 3 studios au 5ème étage en une chambre d'iso2023

Other nearby cases : 02/ENS/1841270, 02/PU/2042435, 02/PP/1906459, 02/PU/1828260, 02/ENS/1966796, 02/PU/1922659, 02/PU/1966811, 02/PU/1955524, 02/PU/2026770, 02/PU/1988663, 02/PU/1801301, 02/PU/1833449, 02/PU/1925153, 02/PU/2038963, 02/PU/2002131, 02/PFU/2001509, 02/PU/1924580, 02/PU/1810179, 02/PU/1953202, 02/PU/1847415, 02/PU/1907206, 02/PU/2019426, 02/PU/1858471, 02/PU/1973241, 02/PU/2011985

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)