Boulevard du Souverain 201

Auderghem · PU/671673 · Permis d'urbanisme privé

Boulevard du Souverain 201, Auderghem: new construction. Case octroyé, lodged on 6 July 1955. The decision was notified on 6 July 1955, 0 days after lodging.

construction école
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on6 July 1955date the file was received
Decision notified6 July 19550 days
Floor areasnot reported by the source
Competent authorityAuderghem

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
41 mChange of usePERMIS OCTROYE PAR LE GVT le 13/08/2026 : transformer et modifier l’ancien couvent en un immeuble de 5 logements avec éq2025
41 mChange of userénover et modifier l'affectation d'un ancien couvent en immeuble de logements collectifs2023
41 mChange of usetransformer et modifier un ancien couvent en un immeuble de 7 logements avec équipement au rez-de-chaussée2025
56 mOtherplacer deux (02) marquises solaires en cassettes au mur de la terrasse de l'appartement A932021
75 mFaçade and windowsisoler par l'extérieur les façades de l'annexe existante et créer une terrasse au rez-de-chaussée d'une maison unifamili2025

Other nearby cases : 02/PFD/2012526, 02/GOU_PU/2025028, 02/ECO/1913238, 02/PFD/1994596, 02/ECO/1994466, 02/PU/1972279, 02/PU/1843614, 02/PU/2014718, 02/ENS/1908670, 02/PU/1860693, 02/PU/1833546, 02/AA/1892559, 02/PU/1962322, 02/PU/1893153, 02/PU/1838298, 02/PU/1847343, 02/PU/1962002, 02/PU/1945530, 02/PU/1922913, 02/PU/1927027, 02/PU/1949551, 02/PU/1907206, 02/PU/1858471, 02/PU/2019426, 02/PU/1870914

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)