Rue de Verdun 163
Bruxelles · PU/672116 · Permis d'urbanisme privé
Rue de Verdun 163, Bruxelles: heavy renovation. Case octroyé, lodged on 14 March 2018. The decision was notified on 4 June 2018, 82 days after lodging.
remplacer les menuiseries en bois en façade avant, créer une lucarne en façade arrière, modifier l'escalier menant au jardin et réaménager l'intérieur du bien (travaux parteillement réalisé)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 March 2018 | date the file was received |
| Decision notified | 4 June 2018 | 82 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 49 m | Façade and windows | repeindre la façade d’une maison | 2026 |
| 72 m | Façade and windows | remplacer le châssis au premier étage et la porte d'entrée au rez-de-chaussée (mise en conformité pour la porte) | 2023 |
| 83 m | New construction | construire un immeuble de 4 logements | 2023 |
| 83 m | New construction | construire un immeuble de 4 logements | 2023 |
| 83 m | New construction | construire un immeuble composé de 3 appartements et d'un parking en sous-sol | 2024 |
Other nearby cases : 04/PU/1833492, 04/PU/1978469, 04/PU/1848580, 04/PU/1824766, 04/LPFD/1823511, 04/PU/1846099, 04/PU/1843223, 04/PU/1894776, 04/PU/1850200, 04/SFD/1862903, 04/PU/1918363, 04/PU/1843193, 04/PU/1850213, 04/PU/1908940, 04/PU/1869779, 04/PU/1926754, 04/SFD/1913137, 04/PU/1826668, 04/PU/1866619, 04/PU/1856814, 04/PU/1800260, 04/PU/1948942, 04/PU/1810716, 04/PU/1899909, 04/PU/1848094
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)