Granted
Rue Konkel 218
Woluwe-Saint-Lambert · PU/675025 · Permis d'urbanisme privé
Rue Konkel 218, Woluwe-Saint-Lambert: merger of dwellings. Case octroyé, lodged on 30 March 2018. The decision was notified on 15 January 2019, 291 days after lodging. It comprises 1 dwellings.
régulariser la transformation de deux appartements en un seul au cinquième étage de l'immeuble1
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 30 March 2018 | date the file was received |
| Decision notified | 15 January 2019 | 291 days |
| Works started | 4 December 2019 | |
| Competent authority | Woluwe-Saint-Lambert |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
- event_works_ended
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 61 m | Regularisation | régulariser les modifications apportées à l'appartement situé au cinquième étage de l'immeuble | 2023 |
| 82 m | Roof | étendre la terrasse existante sur la toiture plate au 5ème étage | 2025 |
| 109 m | Regularisation | régulariser l'appartement 3 chambres au rez-de-chaussée gauche de l'immeuble à appartements | 2023 |
| 127 m | New construction | Maintenir 7 containers classes sur le site pour une durée de 2 ans | 2024 |
| 127 m | New construction | Installer 7 containers temporaires destinés à des classes pour une durée limitée à 2 ans | 2024 |
Other nearby cases : 19/PU/1981996, 18/PU/1947796, 19/AA/1828647, 18/PU/1967845, 19/AA/1831576, 18/PU/1926534, 18/PU/1969670, 18/PU/2035409, 19/GOU_PU/1799810, 18/AA/2016233, 19/PU/2005796, 18/PU/1891865, 18/PFD/1994969, 18/PU/1989945
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)