Skip to content
Altaica Urban
Granted

Place des Acacias 8–9

Etterbeek · PU/676301 · Permis d'urbanisme privé

Place des Acacias 8–9, Etterbeek: office conversion. Case octroyé, lodged on 12 April 2018. The decision was notified on 20 December 2018, 252 days after lodging. The project creates 179 m² of housing. It removes 124 m² of office space. It comprises 5 dwellings.

changer l'affectation des bureaux au rez-de-chaussée, agrandir et diviser les 2 maisons en 5 logements
The application's own description, in its source language (FR). Source: Nova.
179
Housing floor area created
124
Office floor area removed
5
Dwellings created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on12 April 2018date the file was received
Public inquiry27 August 2018 – 11 September 2018
Consultation committee18 September 2018
Decision notified20 December 2018252 days
Works started12 December 2018
Office to housing conversionyes
Competent authorityEtterbeek

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Works started
  8. Decision notified · Granted
  9. event_works_ended

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
9 mSplit into dwellingsdiviser et transformer une maison unifamiliale en 2 duplex, régulariser le placement d'une fenêtre en briques de verre a2025
38 mExtension or raisingrégulariser un auvent au rez-de-chaussée en façade arrière2026
39 mExtension or raisingrégulariser les modification apportées à une maison unifamiliale : annexe, terrasse au 1er étage, aménagement des comble2024
56 mHeavy renovationrénover un immeuble de 4 logements, modifier les balcons, installer un auvent, isoler la façade arrière et la toiture (s2026
58 mExtension or raisingdiviser une maison unifamiliale en deux logements, démolir la verrière, construire une annexe sur deux niveaux et l'isol2025

Other nearby cases : 05/PU/1915517, 05/PU/1979273, 05/PU/2008312, 05/PU/2036205, 05/PU/1859780, 05/PU/1829084, 05/PU/1930264, 05/PU/2036280, 05/PU/1929683, 05/PU/1985475, 05/PU/2013020, 05/PU/2000902, 05/PU/2025615, 05/PU/1996336, 05/PU/1897155, 05/PU/2025494, 05/PU/1899813, 05/PU/1852540, 05/PU/1929797, 05/PU/2025948, 05/PU/1915726, 05/PFD/1912103, 05/PU/1823660, 05/PFD/1928179, 05/PU/1865250

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)