Granted

Rue du Froment 19

Anderlecht · PU/699331 · Permis d'urbanisme privé

Rue du Froment 19, Anderlecht: extension or raising. Case octroyé, lodged on 21 September 2018. The decision was notified on 15 January 2020, 481 days after lodging. The project creates 16 m² of housing.

Extension d'une maison unifamiliale avec démolition de l'annexe-garage
The application's own description, in its source language (FR). Source: Nova.
16
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on21 September 2018date the file was received
Public inquiry19 May 2019 – 3 June 2019
Consultation committee11 July 2019
Decision notified15 January 2020481 days
Works started9 March 2020
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted
  8. Works started
  9. event_works_ended

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
149 mTree fellingabattre un arbre à haute tige2023
149 mTree fellingabattre un arbre à haute tige2024
207 mTree fellingabattre 7 arbres à haute tige (PV2021/3539)2024

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)