Granted
Chaussée de Ninove 269
Molenbeek-Saint-Jean · PU/700899 · Permis d'urbanisme privé
Chaussée de Ninove 269, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 20 June 1902. The decision was notified on 12 June 1903, 357 days after lodging.
la construction d'un bâtiment pour sèchoir| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 20 June 1902 | date the file was received |
| Decision notified | 12 June 1903 | 357 days |
| Floor areas | — | not reported by the source |
| Competent authority | Molenbeek-Saint-Jean |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.