Skip to content
Altaica Urban
Granted

Chaussée de Wavre 562

Etterbeek · PU/701276 · Permis d'urbanisme privé

Chaussée de Wavre 562, Etterbeek: split into dwellings. Case octroyé, lodged on 8 October 2018. The decision was notified on 30 December 2019, 448 days after lodging. The project creates 11 m² of housing. It comprises 3 dwellings.

régulariser la division d'une maison unifamiliale avec commerce en trois logements, rénover l'immeuble et construire un balcon et une lucarne
The application's own description, in its source language (FR). Source: Nova.
11
Housing floor area created
3
Dwellings created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on8 October 2018date the file was received
Consultation committee19 November 2019
Decision notified30 December 2019448 days
Works started1 February 2020
Competent authorityEtterbeek

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Consultation committee
  5. Decision notified · Granted
  6. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
18 mExtension or raisingrégulariser les modifications apportées à une maison unifamiliale : rehausse de la toiture, annexe sur deux niveaux, bai2023
23 mFaçade and windowsplacer une descente d'eaux pluviales en façade avant2023
23 mFaçade and windowsremplacer les châssis en façade avant d'une maison unifamiliale2024
23 mFaçade and windowsRénovation Façade2024
39 mDemolition and reconstructiondémolir et reconstruire le volume au rez arrière, aménager les combles, réorganiser les espaces intérieurs et modifier l2023

Other nearby cases : 05/PU/1971880, 05/PU/1820491, 05/PU/1841328, 05/PU/1827141, 05/PU/2027326, 05/PU/1861243, 05/PU/1916635, 05/PU/1902429, 05/PFD/2037718, 05/PFD/1846857, 05/PFD/2044165, 05/PFD/1908877, 05/PU/1854345, 05/PFU/1943543, 05/PU/1943960, 05/PU/2041004, 05/PU/1839034, 05/PU/1823525, 05/PU/1924389, 05/PU/1896679, 05/PU/1989082, 05/PU/2014336, 05/PU/2037493, 05/PU/2026715, 05/PU/1833254

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)