Avenue Robert Dalechamp 10

Woluwe-Saint-Lambert · PU/702965 · Permis d'urbanisme privé

Avenue Robert Dalechamp 10, Woluwe-Saint-Lambert: regularisation. Case octroyé, lodged on 24 October 2018. The decision was notified on 24 July 2019, 273 days after lodging. The project creates 25 m² of housing.

régulariser les modifications apportées à l'immeuble
The application's own description, in its source language (FR). Source: Nova.
25
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on24 October 2018date the file was received
Public inquiry28 February 2019 – 15 March 2019
Consultation committee29 March 2019
Decision notified24 July 2019273 days
Works started21 September 2020
Competent authorityWoluwe-Saint-Lambert

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted
  8. Works started
  9. event_works_ended

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
6 mFaçade and windowsrégulariser le remplacement des menuiseries extérieures en façade avant et remplacer la porte de garage et la porte d'en2025
8 mTree fellingabattre un arbre dans la zone de recul de l'habitation2023
23 mChange of usesupprimer le commerce à l'avant côté gauche du rez-de-chaussée de l'immeuble pour étendre le logement existant et mainte2026
27 mOffice conversiontransformer le bureau en un appartement de 2 chambres au 1er étage de l'immeuble2026
55 mChange of usemodifier l'affectation d'un commerce en logement, remplacer les portes et châssis et réaménager la zone de recul de l'im2022

Other nearby cases : 18/PU/1899536, 18/PU/1833317, 18/PU/1845040, 18/PU/1831325, 18/PU/1820748, 18/PU/1918716, 18/PU/2020932, 18/PU/2028644, 18/PU/1826007, 18/PU/1910091, 18/GOU_PU/1846307, 18/PU/1968794, 18/PU/1902069, 18/PU/1915504, 18/PU/1988855, 18/PU/1851397, 18/PU/2040357, 18/PU/1850058, 18/PU/1999986, 18/PU/1986750, 18/PU/1902966, 18/PU/1935770, 18/PU/1894948, 18/PU/1997321, 18/PU/1826806

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)