Skip to content
AltUrb
Granted

Boulevard Industriel 198

Anderlecht · 01/IPEPLP/1962670 · Prolongation de PE

Boulevard Industriel 198, Anderlecht: operation of installations. Case octroyé, lodged on 5 November 2024. The decision was notified on 28 October 2025, 357 days after lodging.

Exploitation d'un atelier de réparation de carrosserie automobile
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on5 November 2024date the file was received
Decision notified28 October 2025357 days
Works started20 November 2025
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
59 mSigns and advertisingmaintenir un dispositif publicitaire existant2024
151 mDemolition and reconstructiondémolir les bâtiments existants afin d'agrandir le refuge pour animaux2024
151 mDemolitiondémolir les bâtiments existants afin d'agrandir le refuge pour animaux2024
172 mRoofRénover, isoler la toiture et installer un garde-corps pour la sécurité de l’équipe d’entretien de la toiture et de ses 2024
218 mSigns and advertisingmettre en conformité le maintien d'un dispositif publicitaire de type 8m²2023

Other nearby cases : 01/PU/1857826, 07/PU/1860135

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)