Granted
Boulevard Paepsem 11
Anderlecht · 01/IPEPLP/672281 · Prolongation de PE
Boulevard Paepsem 11, Anderlecht: operation of installations. Case octroyé, lodged on 14 March 2018. The decision was notified on 11 April 2019, 393 days after lodging.
Exploitation d'un immeuble de bureaux - Prolongation| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 March 2018 | date the file was received |
| Decision notified | 11 April 2019 | 393 days |
| Works started | 21 April 2019 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Change of use | changer l'affectation d'espaces de bureaux en espace de stockage (maintien d'un espace bureaux au rez-de-chaussée) | 2025 |
| 133 m | Tree felling | abattre 68 arbres le long des berges de la Senne | 2021 |
| 184 m | New construction | placer une cabine à haute tension préfabriquée | 2021 |
| 184 m | Regularisation | mettre en conformité certains revêtements (perméables) | 2026 |
| 189 m | Demolition and reconstruction | Démolir un immeuble de bureau désaffecté (R+5) et construire un bâtiment comprenant un showroom au rez-de-chaussée et de | 2022 |
Other nearby cases : 01/PFD/1906833, 01/PFD/1949539, 01/PU/1852377