Granted
Place Oscar Ruelens 13
Berchem-Sainte-Agathe · 03/IPE/1708898 · Permis d'environnement
Place Oscar Ruelens 13, Berchem-Sainte-Agathe: operation of installations. Case octroyé, lodged on 4 April 2019. The decision was notified on 19 January 2021, 656 days after lodging.
Uitbating van een school
| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 4 April 2019 | date the file was received |
| Public inquiry | 31 January 2020 – 15 February 2020 | |
| Consultation committee | 2 July 2020 | |
| Decision notified | 19 January 2021 | 656 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | New construction | Construire une crèche provisoire de 34 places | 2022 |
| 0 m | Demolition and reconstruction | Démolir une crèche vétuste et construire un nouveau bâtiment scolaire pour une école primaire avec crèche intégrée, abat | 2023 |
| 0 m | Demolition | Démolir une crèche abritée dans un pavillon indépendant de plain-pied et préparation du terrain pour une future construc | 2022 |
| 0 m | New construction | Un nouveau bâtiment scolaire pour une école primaire avec un jardin d'enfants intégré. Le nouveau bâtiment scolaire est | 2022 |
| 164 m | Heavy renovation | Transformation d'un immeuble (mise en conformité) | 2021 |
Other nearby cases : 03/PU/1811622, 03/PU/1940187, 03/PFU/1866505, 03/PFU/1865556, 03/PU/1829768, 03/PU/2019583, 03/PFD/1933946, 03/PU/2013978, 03/PU/1841775
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)