Granted

Venelle du Champ du Moulin

Berchem-Sainte-Agathe · 03/PFD/199467 · Permis d'urbanisme délivré par le FD

Venelle du Champ du Moulin, Berchem-Sainte-Agathe: new construction. Case octroyé, lodged on 17 July 2008. The decision was notified on 27 February 2009, 225 days after lodging. The project creates 5 249 m² of housing.

Construire un ensemble de logements (maisons individuelles et immeubles à appartements)- Site Gérance
The application's own description, in its source language (FR). Source: Nova.
5 249
Housing floor area created
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on17 July 2008date the file was received
Public inquiry8 October 2008 – 7 November 2008
Consultation committee13 November 2008
Decision notified27 February 2009225 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)