Granted
Avenue du Port 104–106
Bruxelles · 04/IPE/1785965 · Permis d'environnement
Avenue du Port 104–106, Bruxelles: operation of installations. Case octroyé, lodged on 11 May 2021. The decision was notified on 30 November 2021, 203 days after lodging.
centre de tri| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 11 May 2021 | date the file was received |
| Public inquiry | 25 August 2021 – 9 September 2021 | |
| Decision notified | 30 November 2021 | 203 days |
| Works started | 26 November 2021 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Works started
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 129 m | New construction | Construire un nouveau "Stadsatelier de Ville" sur le site de Tour et Taxis à Bruxelles. | 2024 |
| 129 m | New construction | La présente demande concerne une modification du permis déjà obtenu pour la construction du Stadsatelier de Ville, sous | 2025 |
| 176 m | Change of use | Création d'un dépôt de patrimoine pour la Maison du Pain, Musée de la Mode et de la Dentelle avec l'ajout d'ouvertures e | 2022 |
| 178 m | New construction | Construire un ensemble mixte comprenant 89 logements, des commerces, de l'activité productive et un parking souterrain d | 2025 |
| 180 m | Public space | Régulariser des dispositifs mobilier urbain pour l'information. | 2022 |
Other nearby cases : 04/PU/1944446, 04/PU/1870768, 04/SFD/1846408, 04/PU/1831733, 04/PU/1826966, 04/PFD/1851531, 04/PFD/1828327, 04/SFD/1863050, 04/PU/1844314, 04/SFD/1828974, 04/PFD/2023179
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)