Withdrawn

Rue des Eperonniers 41

Bruxelles · 04/IPE/470196 · Permis d'environnement

Rue des Eperonniers 41, Bruxelles: —. Case annulé, lodged on 29 May 2012. The decision was notified on 28 September 2012, 122 days after lodging.

BX3602
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on29 May 2012date the file was received
Public inquiry27 August 2012 – 11 September 2012
Decision notified28 September 2012122 days
Works started26 September 2012
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Works started
  6. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.