Rue Van Artevelde 77–95, Bruxelles: operation of installations. Case octroyé, lodged on 17 August 2012. The decision was notified on 24 June 2013, 311 days after lodging.
renouvellement de pe et remplacement rub 40| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 17 August 2012 | date the file was received |
| Decision notified | 24 June 2013 | 311 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 28 m | Signs and advertising | maintenir un mobilier urbain d’information avec support de publicité (BXL0428) | 2024 |
| 42 m | Extension or raising | diviser une maison unifamiliale en 3 unités de logements (1 duplex et 2 simplex), construire une annexe au rez-de-chauss | 2024 |
| 45 m | Merger of dwellings | réunir deux logements en un appartement au troisième et quatrième étage d’un immeuble de logement (mise en conformité) | 2023 |
| 55 m | Signs and advertising | remplacer 1 mobilier urbain d’information avec support de publicité (BXL0428) | 2022 |
| 74 m | Change of use | changer la destination d'un équipement (résidence pour communauté religieuse) en 4 logements (2 app. 1 ch., 1 duplex 2 c | 2025 |
Other nearby cases : 04/PU/1977425, 04/PFU/1931745, 04/PFU/1871917, 04/PFU/1848820, 04/PU/1990621, 04/PU/1924177, 04/GOU_PU/1827702, 04/PFU/1852907, 04/PU/2044130, 04/PFD/1927157, 04/PFU/1896515, 04/PU/1919048, 04/PU/1856985, 04/PFU/1956218, 04/PU/2017423, 04/PFD/2027887, 04/PU/2025891, 04/PU/2024652, 04/PFD/2025868, 04/PU/1865797, 04/PU/1845784, 04/PFU/1913023, 04/PFU/2037151, 04/PFU/2024113, 04/PU/2024238