Withdrawn

Square Jules De Trooz 19

Bruxelles · 04/IPE/567138 · Permis d'environnement

Square Jules De Trooz 19, Bruxelles: operation of installations. Case annulé, lodged on 3 July 2015. The decision was notified on 25 January 2016, 206 days after lodging.

Bodemsaneringswerven
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on3 July 2015date the file was received
Public inquiry18 September 2015 – 3 October 2015
Consultation committee13 October 2015
Decision notified25 January 2016206 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)